Key production numbers

SamplingSHENGDE targets a physical sample within 15 days after the specification, materials and artwork are confirmed.

BulkBulk production typically takes 25–35 days after sample approval, confirmed in the quotation.

ShippingAir freight to the US is about 1 week; sea freight is about 4–6 weeks, DDP or DDU.

Real riskMost delays come from open decisions — fabric, colour, artwork, sizing — not from sewing time.

Start from the launch date and work backwards

Put the launch date at the end of a calendar and subtract shipping, bulk production, sample approval and sampling. If the result is already in the past, change the shipping method, the scope of the drop or the launch date now — not after the sample arrives.

Leave at least one buffer for a second sample round. A plan with no revision time only works when the tech pack is complete and the first sample is approved without changes.

Stage 1 — tech pack review and quotation

The factory checks the tech pack for missing measurements, fabric details, trims, artwork files, label positions and packaging. Questions should come back as a single written list, and the brand should answer them in one round.

The quotation should be itemized: sample cost, unit price at the quantity per style per colour, decoration, labels, packaging and shipping terms. SHENGDE replies to quote requests within one business day; complex tech packs may need follow-up questions before the price is final.

Stage 2 — materials and pattern

Fabric, rib, zippers, drawcords and labels are confirmed or sourced, and the pattern is made from the tech pack or a reference garment. Colour lab dips or swatches are approved here if exact colour matters.

This is the stage that slips most often. Unconfirmed Pantone references, custom-dyed fabric or special trims extend the calendar more than the sewing itself.

Stage 3 — physical sample and approval

At SHENGDE a physical sample is typically targeted within 15 days after the specification, materials and artwork are confirmed, plus courier time to the brand. Review fit, measurements, fabric, decoration and labels, then send one consolidated comment sheet.

If changes are needed, a revised sample adds roughly another sampling cycle. Bulk production only starts after the buyer approves the physical sample.

Stage 4 — bulk production

After approval and deposit, bulk production at SHENGDE typically takes 25–35 days, confirmed in the quotation. It covers fabric cutting, decoration, sewing, washing where specified, finishing, inspection and packing.

Ask for photo or video updates at fabric inspection, cutting, decoration, sewing and packing. On a short run these updates replace a separately shipped top-of-production sample.

Stage 5 — shipping and delivery

Air freight to the US is about one week; sea freight is about four to six weeks. Under DDP the shipper arranges duties and door delivery; under DDU the buyer handles import duties on arrival. Choose the term before the quotation is final so the landed cost is clear.

For a first drop, many small brands ship by air to protect the launch date, then move repeat orders to sea freight when they can plan further ahead.

A sample calendar for a hoodie drop

Example only, assuming a complete tech pack and one sample round: week 1 tech pack review and quote; weeks 2–3 materials and pattern; weeks 3–5 sample made and couriered; week 6 approval and deposit; weeks 6–11 bulk production; week 12 air freight to the US. Add about three weeks for a second sample round, or about three to five extra weeks for sea freight.

Your actual timeline depends on fabric availability, decoration, quantity and the time you take to approve. Confirm dates in writing for your own project.

How to keep the timeline on track

Send a complete tech pack with measurements and tolerances, approve colours and artwork before sampling, answer questions in one consolidated reply, approve samples within a few days, and decide the shipping term before the quote is final.

Keep one person on the brand side responsible for approvals. Conflicting comments from several people are a common cause of extra sample rounds.

Tech pack to delivery — stages for a 50–500 piece run at SHENGDE

StageTypical durationWhat can delay it
Tech pack review and quoteReply within one business day; final price after open questions are answeredMissing measurements, artwork or fabric details
Materials and patternDepends on fabric and trim availabilityCustom colours, special fabric, unconfirmed trims
Physical sampleTargeted within 15 days after specification, materials and artwork are confirmedLate approvals, design changes
Revision round (if needed)About one more sampling cycleMultiple reviewers, unclear comments
Bulk production25–35 days after sample approval, confirmed in quotationChanges after approval, late deposit
ShippingAir to US about 1 week; sea about 4–6 weeksCustoms documents, peak-season capacity

Frequently asked questions

How long does it take to go from tech pack to finished clothing?

For a small run with one sample round and air freight, plan roughly two and a half to three months. Each extra sample round or sea freight adds time.

How long does bulk production take at SHENGDE?

Typically 25–35 days after sample approval, confirmed in the quotation.

Can production start before the sample is approved?

No. SHENGDE starts bulk production only after the buyer approves the physical sample.

What is the minimum quantity?

From 50 units per style per colour, mixed across sizes, where fabric, colour and decoration allow.

Should I ship by air or sea?

Air protects a launch date for a first drop; sea lowers freight cost when you can plan four to six weeks of transit.

What causes the most delays?

Open decisions on fabric, colour, artwork and sizing, and slow or conflicting sample approvals.

Sources and verification

Official and industry-primary references used to verify standards, regulations and definitions in this guide.

ICC Incoterms questions and answers ↗U.S. Customs textile import guidance ↗

Continue your research

Clothing manufacturing lead time →Types of clothing samples →DDP vs DDU shipping from China →Brand Development Program (tech pack to bulk) →

Put this guidance into production

Review the corresponding SHENGDE product or service page for development options and quotation requirements.

Explore the related capability